Site Diary: June 2024
Work on the Lapis Residence complex is progressing at a steady and well-coordinated pace. Our team of dedicated and experienced professionals is ensuring that every stage of construction goes according to plan and to the highest quality standards.
Block L2:
- We have started installing thermal insulation with basaltic mineral wool.
- The terrace of the block has been completely waterproofed and insulated.
Block L1:
Preparing to pour the slab between floors 3 and 4.
Infrastructure:
The preparation of the road for asphalt paving was started, including grading and compacting the ground.
We are proud of the progress made and are committed to maintaining the pace and quality of the work.